In what situation is a hydrostatic test performed?

  1. Regular maintenance checks

  2. Before commissioning a new boiler

  3. After any repair or modification

  4. Both B and C

The correct answer is: Both B and C

A hydrostatic test is a critical procedure used to assess the integrity and leak-tightness of boilers and pressure vessels. This test involves filling the boiler with water, pressurizing it to a specified level, and then inspecting for any leaks or weaknesses in the structure. It is performed before commissioning a new boiler to ensure that it has been constructed properly and can safely handle operational pressures. On the other hand, it is also essential to conduct hydrostatic tests after any repairs or modifications to confirm that the integrity of the boiler has not been compromised and that it meets safety standards before returning it to service. Given this context, the correct answer encompasses both scenarios, affirming that hydrostatic tests are necessary not only prior to commissioning a new boiler but also following any repair or modification. This ensures safety and regulatory compliance throughout the lifecycle of the boiler.