How many days does a company have to comply with the inspection process after a notice of inspection is issued?

  1. 5 Days

  2. 7 Days

  3. 10 Days

  4. 14 Days

The correct answer is: 7 Days

A company has 7 days to comply with the inspection process after receiving a notice of inspection. This timeframe is established to ensure that inspections are conducted promptly, allowing for any necessary follow-up actions or repairs to be addressed without significant delays. Timely compliance helps maintain safety standards and ensures that boilers are operating efficiently and within regulatory guidelines. Understanding and adhering to this timeframe is essential for companies to avoid potential fines or penalties that may arise from non-compliance.